Newton is proud to contribute to the transformation of the unique, Grade I listed Cambridge House in Piccadilly as it undergoes conversion into one of London’s grandest hotels. The 18,000m2 scheme includes six adjacent Grade II listed residences, whilst a four-level basement will accommodate a spa as well as the back-of-house and servicing areas.

The Project

In order to deliver a reliable, watertight solution for this project, Newton worked closely with architects PDP London and leading enabling works contractor Deconstruct UK throughout the design and installation.

There are three main buildings where extensive excavations are taking place, requiring different waterproofing solutions to cater for the new-build basement areas and existing elements - all up to 4 storeys below ground.

The Solution

Buildings 1 and 3 are both benefiting from full Newton CDM System cavity drain membrane waterproofing, which will capture, depressurise and remove any ingressing ground water via a series of Trojan-Pro pump chambers.

Building 2 utilises numerous products across new/existing structures, including 403 HydroBond, installed by NSBC Maclennan Waterproofing, and 315 Polymer-Waterbar to the new concrete attenuation tank, which will also be coated internally with the 103-S liquid membrane.

The same two products were also used alongside the flexible 107F liquid membrane and 106 FlexProof for construction joint waterproofing in areas where the existing brick structure interfaces with a new concrete slab. Finally, Titan-Pro pump chambers are being installed to remove the water.

The Result

As of June 2021, the waterproofing installation is underway and on-track on all three buildings, with Newton’s site services team delivering an exceptional quality assurance and training service on the installation of our products.

quotation marks

Newton Waterproofing have been working with Deconstruct to provide waterproofing design and solutions at Cambridge House. The project encompassed forming new deep Basement excavations, Grade 1 and Grade 2 listed structures requiring significant interventions and all requiring a Grade 3 level of waterproof protection. Newton have been involved from the outset and have provided a first class service to ensure we provide a robust solution to this prestigious project. Mark Makinson, Project Director - Deconstruct UK Ltd

Speak to our friendly, expert team

Our staff are able to provide guidance for projects of all sizes, whether you require some general advice about damp or waterproofing, or support with technical drawings and specifications.


    By submitting your details you confirm that you agree to the storing and processing of your personal data by Newton Waterproofing as described in the privacy statement.

    We will be closing between Christmas and New Year, with the last day of operations being Friday 20th December. Last orders for delivery before Christmas therefore need to be placed by 2pm on Thursday 19th December, with final deliveries on Friday 20th December. After this, no deliveries will be possible until January 2025. The Newton branches in Tonbridge and Leeds will reopen in the New Year on Thursday 2nd January 2025.