Summary

Mace Group’s redevelopment of Warwick Court in Paternoster Square, London, involved expanding the floor space to 300,000 sq ft. The project has two basement levels that were required to accommodate plant rooms, a car park and loading bay.

The Project

Warwick Court, the former Goldman Sach's headquarters on Paternoster Square in London, is being redeveloped by Mace Group after they won the project in 2020. The development involves expanding the floor space to 300,000 sq ft, following a plan drawn up by architect Fletcher Priest. As part of the large scale redevelopment project, two basement levels were required to accommodate a car park, loading bay, plant rooms and storage.

The Solution

Mace approached Newton and our specialist contractor ASF Waterproofing to specify a waterproof and hard-wearing coating system for the floor of the plant rooms. As a result, ASF Waterproofing designed and installed a watertight system utilising Newton 110 WATstop and Newton 701-HB.

Firstly, after the surface had been properly prepared, the fibre-reinforced cement/epoxy workable mortar 110 WATstop was applied as a waterproofing layer to the floor of the plant rooms, providing a smooth surface that also repairs the surface of concrete.

Secondly, the epoxy resin-based floor coating 701-HB, was applied afterwards to provide a hard-wearing coating to protect the waterproofing layer. ASF mixed in kiln-dried sand to the first coat for added grip, making the floor safer to walk on.

The Result

ASF Waterproofing provided a completely watertight solution following the guidelines set out in BS 8102:2009. The works were carried out to a high standard and delivered on time, despite the tight schedule.

Newton are proud to have been involved in this project, run by property developer Stanhope, who ran the development with an all-female senior team for the first time, setting a benchmark for the future of women in construction.

quotation marks

"Having the opportunity to work with Newton Waterproofing and ASF Waterproofing Specialists on this project has been absolutely delightful, not only have the team installing the product been faultless, the finished article is outstanding. We are proud to have worked closely with both Newton's and ASF to meet our client's needs and programme requirements, the advice, guidance and support of both businesses is second to none and I would highly recommend using them on all projects moving forward." - Reece Hardy, Associate Director - Construction at Mace Group.

Speak to our friendly, expert team

Our staff are able to provide guidance for projects of all sizes, whether you require some general advice about damp or waterproofing, or support with technical drawings and specifications.


    By submitting your details you confirm that you agree to the storing and processing of your personal data by Newton Waterproofing as described in the privacy statement.

    We will be closing between Christmas and New Year, with the last day of operations being Friday 20th December. Last orders for delivery before Christmas therefore need to be placed by 2pm on Thursday 19th December, with final deliveries on Friday 20th December. After this, no deliveries will be possible until January 2025. The Newton branches in Tonbridge and Leeds will reopen in the New Year on Thursday 2nd January 2025.