Newton were approached by the desperate client at this large terraced property in Notting Hill, having had a second basement level excavated beneath the existing basement and the front and rear gardens.
Unfortunately, bad waterproofing design and workmanship meant the basement had flooded immediately upon completion – the builder ceased trading and, following a legal case, the architect and structural engineer were found culpable.
Newton recommended our experienced specialist contractor Stonehouse in order to assess the failure and propose a comprehensive solution.
The experts at Stonehouse identified a litany of issues, from the weak, permeable structure to the lack of continuous waterproofing between levels, the inadequate pumping system, the blocked cavity drain system, and the non-existent external deck waterproofing and drainage, amongst others.
Once structural reinforcement had taken place, Stonehouse proceeded by:
Stonehouse delivered an exceptional waterproofing design and installation for the client, who now has a watertight and guaranteed two-level basement beneath their home, that they can enjoy in full for the first time in many years.
"This was probably the most technically challenging project Stonehouse have ever undertaken. But with clients who wanted no future risk of water ingress, we were able to design and intall a robust, durable solution utilising the full range of Newton waterproofing products to prevent water ingress from all conceivable directions. As a result, the client can finally enjoy the vast space below their house with the reassurance of our long-term guarantee." Graham Stone - Managing Director, Stonehouse
Our staff are able to provide guidance for projects of all sizes, whether you require some general advice about damp or waterproofing, or support with technical drawings and specifications.
We will be closing between Christmas and New Year, with the last day of operations being Friday 20th December. Last orders for delivery before Christmas therefore need to be placed by 2pm on Thursday 19th December, with final deliveries on Friday 20th December. After this, no deliveries will be possible until January 2025. The Newton branches in Tonbridge and Leeds will reopen in the New Year on Thursday 2nd January 2025.