This multi-million pound Listed property was refurbished, extended and waterproofed by Wing Waterproofing with Newton System 500.
A spectacular multi-million pound listed property on the Thames
Newton Waterproofing Systems offer extensive solutions when waterproofing riverside properties. This spectacular multi-million pound listed property on the Thames was being completely refurbished and extended to provide a large modern property, yet retain the features of the original design.
As a large section of the project was below ground level and metres from the River Thames, a robust and reliable waterproofing approach was essential. Newton Specialist Basement Contractor Wing Waterproofing were commissioned to undertake the project. The project had a series of existing vaulted arches and brick walls to the front of the property which were underpinned to create the extra living space required.
To the rear of the property a very large RC concrete box was cast to provide a new subterranean living space, coupled with a large swimming pool. Wing Waterproofing used Newton 101F as a cementitious Type A barrier system across all underpinned sections to provide a resistance to water coming through the dry pack elements. New-build joints in the RC box were protected by Newton 303 PolyProof water bars encased in the new shuttered box in all the vaulted areas.
Newton 508 membrane was installed and batten hung off the plugs. Any water would be diverted to the Newton Basedrain which was fitted around the perimeter of the entire structure. Prior to the membrane system being installed a new RC slab was installed throughout both elements of construction. The engineered slab had concrete sumps formed within the structure as a means of capturing the water that entered the system and to be removed via mechanical means. Newton 906 Lime Inhibitor was used on the slab, 50mm of closed cell insulation was installed as a spacer on the slab and the Newton 508 was installed with a 65 screed with underfloor heating to finish.
Both new-build and existing building elements were waterproofed to a Grade 3 habitable environment in accordance with BS 8102:2009. This project was in an extremely high risk area being metres for the Thames and the skill of the main contractor interfacing with NSBC Wing Waterproofing ensured the client had a watertight structure.
The projection of the joints with the contingency of the Cavity Drain means the system is “maintainable” a prerequisite when designing waterproofing systems to BS8102:2009. Wing Waterproofing took PI on the design and installation so the client has an insured backed guarantee for all works.
Our staff are able to provide guidance for projects of all sizes, whether you require some general advice about damp or waterproofing, or support with technical drawings and specifications.
We will be closing between Christmas and New Year, with the last day of operations being Friday 20th December. Last orders for delivery before Christmas therefore need to be placed by 2pm on Thursday 19th December, with final deliveries on Friday 20th December. After this, no deliveries will be possible until January 2025. The Newton branches in Tonbridge and Leeds will reopen in the New Year on Thursday 2nd January 2025.